Track maintenance & track machines — questions with answers

33 questions on track maintenance & track machines, each with the answer and where it comes from. Try each one before you tap Show answer.

Take these as a scored test

Answer them against the clock and see your score with every answer explained.

Start set 1 Start set 2

Questions

Q1.To assess ballast needed for deep screening, the section is screened to full depth over 2-3 sleepers at intervals of ______.

  1. 100 to 200 m
  2. 0.5 to 1 km
  3. 2 to 3 km
  4. 5 km
Show answer

Answer: (B) 0.5 to 1 km

A trial deep screening of 2-3 sleepers to full depth is done every 0.5 to 1 km to assess recoupment needs.

Source: RailPro e-book Vol 1, page 283

Q2.Which statement about tamping machines is correct?

  1. They can lower track up to 25 mm
  2. They cannot correct alignment
  3. They cannot lower the track
  4. They do not measure track geometry
Show answer

Answer: (C) They cannot lower the track

Tamping machines can only lift; they use a proportional levelling system to measure and correct geometry.

Source: RailPro e-book Vol 2, page 622

Q3.The desirable gap between top edge of the tamping blade and bottom edge of PSC / flat bottom sleeper is ___________________________

  1. 10- 12 mm
  2. 15-20 mm
  3. 20 -22 mm
  4. 22-25 mm
Show answer

Answer: (B) 15-20 mm

Source: JE (P.Way) Question Bank 2025, Q.1460

Q4.Shoulder ballast screening, done as preventive maintenance, is carried out once in ______.

  1. 3 years
  2. 1 year
  3. 5 years
  4. 10 years
Show answer

Answer: (A) 3 years

Shoulder screening is preventive maintenance done once in 3 years. Deep screening is breakdown maintenance; since the 2021 revised norms it is triggered by the clean ballast cushion falling below the limit, not by a fixed 10-year cycle.

Source: RailPro e-book Vol 1, page 233

Q5.Compared with UNIMAT 2S, the UNIMAT 3S has ______.

  1. Two tamping units per rail
  2. An extra lifting hook for the third rail
  3. A ballast cleaning unit
  4. A dynamic stabiliser
Show answer

Answer: (B) An extra lifting hook for the third rail

UNIMAT 2S lifts at one point per rail; 3S has an additional hook to lift the third rail, so it handles crossing cross-level better.

Source: RailPro e-book Vol 2, page 541

Q6.Net ballast quantities assessed for maintenance are enhanced by about ______ to arrive at gross procurement quantities when measured in stacks or wagons at origin.

  1. 8%
  2. 2%
  3. 15%
  4. 25%
Show answer

Answer: (A) 8%

The net quantity is suitably increased, say by 8%, to get gross quantities for procurement.

Source: RailPro e-book Vol 1, page 284

Q7.Which of the following machine is point tamping machine.

  1. VDM-800
  2. PTV-800
  3. Unimat 08-275
  4. DGS -62 –N
Show answer

Answer: (C) Unimat 08-275

Source: JE (P.Way) Question Bank 2025, Q.1438

Q8.The test pieces 1m length (500mm + 500mm) for metallurgical examination are to be sent only for rail failures which occur

  1. within first 25% of service life subject to maximum of 10 years of rolling
  2. In case of repetitive failures of rails of same rolling mark
  3. The rail where rail/ weld failure is prima facie cause of train accident
  4. All the above
Show answer

Answer: (D) All the above

Source: JE (P.Way) Question Bank 2025, Q.1418

Q9.Approximately how long does UNIMAT 08-475 4S take to tamp one 1 in 12 turnout?

  1. 90-100 minutes
  2. 30-40 minutes
  3. 3-4 hours
  4. 15-20 minutes
Show answer

Answer: (A) 90-100 minutes

The notes state 90-100 minutes are required for one 1:12 turnout.

Source: RailPro e-book Vol 2, page 543

Q10.The annual machine deployment program for track renewal, rail grinding and deep screening shall be issued by ______________

  1. PCE
  2. CTE
  3. Sr. DEN Co.
  4. CE/TM
Show answer

Answer: (B) CTE

Source: JE (P.Way) Question Bank 2025, Q.1316

Q11.Deep screening by BCM results in __________________

  1. Improving the Drainage of track
  2. Improvement of track resilience
  3. Improvement of elasticity of ballast bed
  4. All the above
Show answer

Answer: (D) All the above

Source: JE (P.Way) Question Bank 2025, Q.1501

Q12.The squeezing pressure recommended for tamping PSC sleepers is ______.

  1. 90 bar
  2. 100 bar
  3. 130 bar
  4. 110 bar
Show answer

Answer: (D) 110 bar

Squeezing pressure: wooden 90 bar, CST/steel 100 bar, PSC 110 bar.

Source: RailPro e-book Vol 2, page 613

Q13.Tamping depth to be set on the machine for PSC sleepers with 60 kg rails (sleeper 210 mm, rail 172 mm, liner 5 mm) is ______.

  1. 382 mm
  2. 387 mm
  3. 355 mm
  4. 392 mm
Show answer

Answer: (B) 387 mm

Depth = sleeper height + rail height + liner height = 210 + 172 + 5 = 387 mm.

Source: RailPro e-book Vol 2, page 611

Q14.At the beginning of the gang beat ___no. of rails sample track should be maintained

  1. 1
  2. 2
  3. 3
  4. 4
Show answer

Answer: (C) 3

Source: JE (P.Way) Question Bank 2025, Q.1336

Q15.After a turnout is laid by T-28, how many rounds of UNIMAT tamping are to be done after ballasting before normalising speed?

  1. 1
  2. 2
  3. 5
  4. 3
Show answer

Answer: (D) 3

Post-block, 3 rounds of tamping are done before normal speed, plus one more after about three months.

Source: RailPro e-book Vol 2, page 654

Q16.Which of the following is NOT a basic unit of a Ballast Cleaning Machine?

  1. Excavating unit
  2. Screening unit
  3. Track lifting and slewing device
  4. Tamping unit
Show answer

Answer: (D) Tamping unit

BCM units are excavating, screening, conveyor, track lift/slew and recording units; tamping is done by a separate machine.

Source: RailPro e-book Vol 2, page 554

Q17.For correcting the longitudinal profile, on straight track on double line, the datum rail selected is ______________________________________

  1. Inner rail
  2. Outer rail
  3. less disturbed rail
  4. Cess side rail
Show answer

Answer: (C) less disturbed rail

Source: JE (P.Way) Question Bank 2025, Q.1480

Q18.JE/P.Way shall inspect all side drains, catch water drains and bridge waterways at least once a year in the month of ______.

  1. June
  2. September
  3. April
  4. December
Show answer

Answer: (C) April

As per IRPWM, JE/P.Way inspects these drains once a year in April, before the monsoon.

Source: RailPro e-book Vol 1, page 381

Q19.Auxiliary track of _______ mm gauge should be laid to run portal cranes in TLE

  1. 1676
  2. 3400
  3. 4265
  4. 5300
Show answer

Answer: (B) 3400

Source: JE (P.Way) Question Bank 2025, Q.1522

Q20.The Shoulder Ballast Cleaning Machine (FRM-80/KSC-600) is provided with ______.

  1. One cutter chain under the sleepers
  2. Two excavating cutter chains, one on each side
  3. Four tamping units
  4. A single broom at the rear
Show answer

Answer: (B) Two excavating cutter chains, one on each side

FRM has two cutter chains, one on either side, to pick up and screen shoulder ballast.

Source: RailPro e-book Vol 2, page 579

Q21.Maximum centre to centre sleeper spacing on steel girder except at cross girder in open web girders bridges should be ______________

  1. 450mm
  2. 500mm
  3. 600mm
  4. 700mm
Show answer

Answer: (C) 600mm

Source: JE (P.Way) Question Bank 2025, Q.1397

Q22.The Dynamic Track Stabiliser works by ______.

  1. Horizontal oscillation of the track with a static vertical load
  2. Vertical vibration with tamping tines
  3. Lifting and dropping the track
  4. Compressing shoulder ballast only
Show answer

Answer: (A) Horizontal oscillation of the track with a static vertical load

DTS sets the track in horizontal oscillation while applying a static vertical load, so ballast re-arranges and the track settles.

Source: RailPro e-book Vol 2, page 583

Q23.For mechanised maintenance, the clean ballast cushion under the rail seat of PSC sleepers shall at no time be less than ______.

  1. 100 mm
  2. 200 mm
  3. 250 mm
  4. 150 mm
Show answer

Answer: (D) 150 mm

Minimum 150 mm clean cushion under PSC rail seat must be maintained at all times for mechanised maintenance.

Source: RailPro e-book Vol 1, page 224

Q24.Thickness of painting on rails is measured with ____________

  1. Anemometer
  2. Tachometer
  3. Pyrometer
  4. Elco meter
Show answer

Answer: (D) Elco meter

Source: JE (P.Way) Question Bank 2025, Q.1357

Q25.As a maintenance practice side drains, catch water drains and bridges to be cleaned in ____________________

  1. Pre Monsoon attention
  2. During Monsoon attention
  3. Post Monsoon attention
  4. Any of the above
Show answer

Answer: (A) Pre Monsoon attention

Source: JE (P.Way) Question Bank 2025, Q.1377

Q26.As per the Railway Board's revised norms of 2021, deep screening of plain track on the main line with sectional speed of 130 kmph and above is due when the clean ballast cushion is less than ______.

  1. 150 mm
  2. 200 mm
  3. 250 mm
  4. 300 mm
Show answer

Answer: (B) 200 mm

The 2021 revised norms (10th Extraordinary TSC) replaced the old '500 GMT or 10 years' rule with cushion-based criteria: deep screen main-line plain track when clean cushion is below 200 mm for 130 kmph and above (below 150 mm for lower speeds); turnouts on the main line below 200 mm; loop lines once in 15 years.

Source: RailPro e-book Vol 1, page 233

Q27.After grinding, __________ should be cleaned from __________ joints.

  1. Grind dust, glued
  2. Grease, glued
  3. Grind dust, FP
  4. All the above
Show answer

Answer: (A) Grind dust, glued

Source: JE (P.Way) Question Bank 2025, Q.1542

Q28.Tamping tools vibrate at a frequency of about ______, at which ballast behaves like a fluid.

  1. 35 Hz
  2. 45 Hz
  3. 20 Hz
  4. 50 Hz
Show answer

Answer: (A) 35 Hz

Tool vibration is 35 Hz with 10 mm amplitude, easing penetration with minimum ballast damage.

Source: RailPro e-book Vol 2, page 612

Q29.A major advantage of dynamic track stabilisation is ______.

  1. Lowering of track by 50 mm
  2. Elimination of tamping
  3. Increased lateral resistance of track
  4. Cleaning of ballast
Show answer

Answer: (C) Increased lateral resistance of track

DTS consolidates the ballast bed homogeneously, raises lateral resistance and reduces buckling risk.

Source: RailPro e-book Vol 2, page 596

Q30.Deep screening of a PSC turnout by RM-80-92U requires a traffic block of about ______.

  1. 5 hours
  2. 2 hours
  3. 3.5 hours
  4. 8 hours
Show answer

Answer: (C) 3.5 hours

Block needed: RM-80-92U about 3.5 h, RM-76 about 5.0 h.

Source: RailPro e-book Vol 2, page 573

Q31.The maximum load capacity of each portal crane of the T-28 turnout renewal machine is ______.

  1. 25 tonnes
  2. 30 tonnes
  3. 20 tonnes
  4. 40 tonnes
Show answer

Answer: (B) 30 tonnes

T-28 portal crane capacity is 30 t; its motorised trolley capacity is 25 t.

Source: RailPro e-book Vol 2, page 627

Q32.The maximum vertical load applied by the hydraulic cylinders of DTS model DGS-62N is about ______.

  1. 110 kN
  2. 45 kN
  3. 600 kN
  4. 356 kN
Show answer

Answer: (D) 356 kN

DGS-62N applies vertical load up to 356 kN, with oscillation frequency of 0-45 Hz.

Source: RailPro e-book Vol 2, page 587

Q33.A limitation of the T-28 portal crane is that with load it ______.

  1. Can travel on crawlers only
  2. Can travel on rail wheels only
  3. Cannot be moved at all
  4. Needs a power block
Show answer

Answer: (A) Can travel on crawlers only

T-28 cannot travel on rail wheels with load; it moves on crawlers when loaded.

Source: RailPro e-book Vol 2, page 633

‹ Schedule of Dimensions (IRSOD)All RailPro topicsSmall track machines ›

Preparing for AE / JE exams?
Get new civil engineering vacancies on Telegram, posted automatically every day. Free to join.
Join on Telegram ›