Plaster Quantity Calculation: Cement and Sand per 100 m²

10 October 2026

For 100 m² of 12 mm thick cement plaster in 1:6 you need about 7.5 bags of cement (376 kg) and 1.57 m³ of sand (about 55 cft). For 20 mm plaster, a 1:4 mix needs about 17.6 bags of cement and 2.44 m³ of sand, and a 1:6 mix needs about 12.5 bags and 2.61 m³ of sand.

These figures include 20% extra for uneven surfaces, joint filling and wastage, plus a wet-to-dry factor of 1.27. Below is the method, so you can repeat it for any area, thickness or mix.

The method in four steps

  1. Wet volume = plastered area × thickness. For example, 100 m² × 0.012 m = 1.2 m³.
  2. Add for uneven surfaces and wastage. Brick walls are never perfectly true, and the mortar also fills the raked joints. Add 20% for this.
  3. Convert to dry volume. Dry cement and sand contain voids that disappear when you add water, so multiply by 1.27.
  4. Split by the mix ratio. For 1:6, cement is 1/7 and sand is 6/7 of the dry volume. Cement weighs 1440 kg/m³, so one 50 kg bag is 0.0347 m³. One m³ is 35.31 cft.
Practice varies. Some engineers use a dry factor of 1.33 or 1.35 and add only 10% for wastage. Others add 30% on very rough walls. The combined factor used here is 1.20 × 1.27 = 1.52. A combined factor of 1.33 × 1.10 = 1.46 gives about 4% less material. Choose one convention, state it in your estimate and use it consistently.

Which thickness and mix is used where

Common Indian practice is listed below, but always follow the project specification.

  • 12 mm, 1:6 on internal walls on the fair (smooth) side of brickwork
  • 15 mm, 1:6 on the rough side of a wall
  • 20 mm, 1:4 or 1:6 on external walls, often in two coats
  • 6 mm, 1:3 on RCC ceilings

12 mm plaster in 1:6: per 100 m²

  1. Wet volume = 100 × 0.012 = 1.20 m³
  2. Add 20%: 1.20 × 1.20 = 1.44 m³
  3. Dry volume = 1.44 × 1.27 = 1.829 m³
  4. Cement = 1.829 ÷ 7 = 0.2613 m³ × 1440 = 376 kg = 7.5 bags
  5. Sand = 1.829 × 6/7 = 1.568 m³ ≈ 55.4 cft

20 mm plaster in 1:4 and 1:6: per 100 m²

  1. Wet volume = 100 × 0.020 = 2.00 m³
  2. Add 20%: 2.00 × 1.20 = 2.40 m³
  3. Dry volume = 2.40 × 1.27 = 3.048 m³
  4. 1:4 (5 parts): cement = 3.048 ÷ 5 = 0.6096 m³ = 878 kg = 17.6 bags, and sand = 3.048 × 4/5 = 2.438 m³ ≈ 86 cft
  5. 1:6 (7 parts): cement = 3.048 ÷ 7 = 0.4354 m³ = 627 kg = 12.5 bags, and sand = 3.048 × 6/7 = 2.613 m³ ≈ 92 cft

Quick reference table

Thickness and mixDry mortar (m³)Cement (bags)Cement (kg per m²)Sand (m³)Sand (cft)
6 mm, 1:3 (ceiling)0.9146.63.30.68624.2
12 mm, 1:41.82910.55.31.46351.7
12 mm, 1:61.8297.53.81.56855.4
15 mm, 1:62.2869.44.71.95969.2
20 mm, 1:43.04817.68.82.43886.1
20 mm, 1:63.04812.56.32.61392.3

All quantities except cement kg per m² are per 100 m² of plaster, with 20% added for surface and wastage and a dry factor of 1.27.

Worked example: plastering one room

The room is 4.0 m × 3.5 m on plan with 3.0 m clear height. It has one door (1.0 × 2.1 m) and two windows (1.2 × 1.2 m each). The walls get 12 mm plaster in 1:6 and the ceiling gets 6 mm plaster in 1:3.

Walls

  1. Gross wall area = perimeter × height = 2 × (4.0 + 3.5) × 3.0 = 45.0 m²
  2. Openings = door 2.10 + windows 2 × 1.44 = 4.98 m²
  3. Net area = 45.0 − 4.98 = 40.02 m²
  4. Wet volume = 40.02 × 0.012 = 0.480 m³
  5. Add 20%: 0.480 × 1.20 = 0.576 m³
  6. Dry volume = 0.576 × 1.27 = 0.732 m³
  7. Cement = 0.732 ÷ 7 = 0.1046 m³ × 1440 = 151 kg ≈ 3.0 bags
  8. Sand = 0.732 × 6/7 = 0.627 m³ ≈ 22.2 cft

Ceiling

  1. Area = 4.0 × 3.5 = 14.0 m², so the wet volume = 14.0 × 0.006 = 0.084 m³
  2. Adding 20% gives 0.1008 m³, and multiplying by 1.27 gives a dry volume of 0.128 m³
  3. Cement = 0.128 ÷ 4 = 0.032 m³ = 46 kg ≈ 0.9 bag
  4. Sand = 0.128 × 3/4 = 0.096 m³ ≈ 3.4 cft

Total for the room: about 197 kg of cement (3.9 bags, so buy 4) and 0.72 m³ of sand (about 25.5 cft).

For material estimates, deduct the actual opening area and add the jambs, sills and soffits (the reveals) separately if they are plastered. For billing, IS 1200 has its own rules for deducting openings and adding reveals, so the billed area may differ from the area you use to order material.

To get plaster, brickwork and concrete quantities for a whole house together, use the Nirmaan house estimator.

Site tips and common mistakes

  • Ordering on wet volume. Using area × thickness alone under-orders by about a third.
  • Ignoring bulking of sand. Damp sand measured by volume bulks noticeably, often by 15–30% depending on moisture. Batch with dry sand or correct for bulking, or the plaster ends up lean.
  • Using a thick coat to hide bad brickwork. Every extra 5 mm adds about 40% to a 12 mm plaster's material. Check the wall for plumb before you start plastering.
  • Skipping preparation. Rake the joints, hack smooth concrete surfaces and wet the wall before plastering. Fix level dots and screeds so the thickness stays even.
  • Poor curing. Keep the plaster moist for at least 7 days, as is common practice. See curing of concrete. PPC suits plaster work well, as explained in OPC vs PPC vs PSC.

Frequently asked questions

How much cement is needed for 100 m² of 12 mm plaster?

About 7.5 bags (376 kg) of cement and 1.57 m³ of sand for a 1:6 mix. This includes 20% for uneven surfaces and wastage and a dry factor of 1.27.

What is the dry volume factor for plaster?

Wet mortar volume is usually multiplied by 1.27 to get the dry volume of cement and sand. Some engineers use 1.33 or 1.35 instead. Wastage and surface unevenness are added separately, typically 10% to 30%.

How much cement is needed per m² of plaster?

Roughly 3.8 kg per m² for 12 mm plaster in 1:6, 6.3 kg per m² for 20 mm in 1:6 and 8.8 kg per m² for 20 mm in 1:4. The exact figure depends on your wastage assumption.

Which plaster mix is used for external walls?

External walls usually get 18 to 20 mm plaster in 1:4 or 1:6, often in two coats. Always follow the project specification.

Estimating a whole house? Nirmaan Estimator works out concrete, steel (with a full bar bending schedule), bricks, plaster and cost from just the plinth area and number of storeys — free for a G+0 house up to 800 sft.

Open Nirmaan Estimator ›
Preparing for AE / JE exams?
Get new civil engineering vacancies on Telegram, posted automatically every day. Free to join.
Join on Telegram ›