Engineering restrictions & indicators — questions with answers

12 questions on engineering restrictions & indicators, each with the answer and where it comes from. Try each one before you tap Show answer.

Take these as a scored test

Answer them against the clock and see your score with every answer explained.

Start the test

Questions

Q1.The Siding ‘S' marker indicator shall be fixed at a height of ______ metres from the Rail Level to Centre of indicator.

  1. 2.5 m
  2. 2.2 m
  3. 2.0 m
  4. 1.65 m
Show answer

Answer: (C) 2.0 m

Source: JE (P.Way) Question Bank 2025, Q.553

Q2.For carrying out track works requiring stop dead restriction, the stop indicator shall be fixed at a height of _______ metres from the Rail Level to bottom of indicator.

  1. 3.0 m
  2. 2.5 m
  3. 2.0 m
  4. 1.65 m
Show answer

Answer: (C) 2.0 m

Source: JE (P.Way) Question Bank 2025, Q.540

Q3.What is the Dimension of T/LOOP indicator

  1. 1.40 m dia
  2. 1.0 m on each side
  3. 1.0 m dia
  4. 0.90m dia
Show answer

Answer: (C) 1.0 m dia

Source: JE (P.Way) Question Bank 2025, Q.546

Q4.During works of long duration, the temporary engineering fixed signals should be fixed a distance from work spot when the trains required to proceed at restricted speed are

  1. Caution indicator at 1200 mts, speed indicator at 30 mts
  2. Caution indicator at 800 mts, speed indicator at 30 mts
  3. Caution indicator at 1200 mts, speed indicator at 600 mts
  4. Caution indicator at 800 mts, speed indicator at 100 mts
Show answer

Answer: (A) Caution indicator at 1200 mts, speed indicator at 30 mts

Source: JE (P.Way) Question Bank 2025, Q.519

Q5.The staff required for fixing hand signal of keyman / patrolman should be at a height of _______

  1. 3 feet
  2. 4 feet
  3. 5 feet
  4. 6 feet
Show answer

Answer: (C) 5 feet

Source: JE (P.Way) Question Bank 2025, Q.533

Q6.Works of long duration are those works which are completed

  1. Within three hours
  2. within 6 hours
  3. Taking more than a day
  4. none of these
Show answer

Answer: (C) Taking more than a day

Source: JE (P.Way) Question Bank 2025, Q.512

Q7.In track works in case movement of vehicle is within 3.5m from track centre it is permitted when

  1. Presence of look out men authorized by Engineer in charge with protection equipment
  2. Contractor supervisor and Railway supervisor
  3. Issuing of Whistle free or requisite caution order and Traffic block
  4. All of the above full filled.
Show answer

Answer: (D) All of the above full filled.

Source: JE (P.Way) Question Bank 2025, Q.560

Q8.During emergency protection, the protection person unable to reach 600m or 1200m for placing single or 3 detonators respectively, when he see approaching train, what action can take by the protection person

  1. Immediately show the danger hand signal
  2. Immediately fix 3 detonators and show the danger hand signal
  3. Immediately fix 2 detonators and show the danger hand signal
  4. Immediately fix 1 detonator and show the danger hand signal
Show answer

Answer: (D) Immediately fix 1 detonator and show the danger hand signal

Source: JE (P.Way) Question Bank 2025, Q.499

Q9.At Rail/Weld fracture location, after emergency repairs are completed with approved High Performance Rail Clamps (HPRC) and there is 24hrs watch, after first train subsequent trains should pass at a speed of ______

  1. 50 kmph
  2. 30 kmph
  3. 20 kmph
  4. 15 kmph
Show answer

Answer: (A) 50 kmph

Source: JE (P.Way) Question Bank 2025, Q.505

Q10.During long duration works when the train is required to stop and proceed, the Flag man posted at stop indicator should take the signature of the train driver in a Book called

  1. Train dairy
  2. Restriction book
  3. flagman dairy
  4. None of these
Show answer

Answer: (B) Restriction book

Source: JE (P.Way) Question Bank 2025, Q.526

Q11.What is the Dimension of Banner flag is

  1. 1.50 m X 0.45 m
  2. 1.70 m X 0.50 m
  3. 1.40 m X 0.40 m
  4. 1.80 m X 0.60 m
Show answer

Answer: (A) 1.50 m X 0.45 m

Source: JE (P.Way) Question Bank 2025, Q.491

Q12.Stop Dead restrictions, for stopping trains ______ signal should be shown alternate to red flag during day time

  1. One Arm rise above the shoulder
  2. One Arm rise above the head
  3. Both Arms rise above the shoulder
  4. Both Arms rise above the head
Show answer

Answer: (D) Both Arms rise above the head

Source: JE (P.Way) Question Bank 2025, Q.483

‹ Stations, train working & block systemsAll RailPro topicsTrolleys, lorries & rail dollies ›

Preparing for AE / JE exams?
Get new civil engineering vacancies on Telegram, posted automatically every day. Free to join.
Join on Telegram ›