Trolleys, lorries & rail dollies — questions with answers

12 questions on trolleys, lorries & rail dollies, each with the answer and where it comes from. Try each one before you tap Show answer.

Take these as a scored test

Answer them against the clock and see your score with every answer explained.

Start the test

Questions

Q1.Contractors and their agents may be conveyed on trolley in connection with railway works

  1. with permission of competent authority and executing general Indemnity bond
  2. without competent authority permission but person executing Indemnity bond
  3. with permission from competent authority but Indemnity bond no required
  4. None of the above
Show answer

Answer: (A) with permission of competent authority and executing general Indemnity bond

Source: JE (P.Way) Question Bank 2025, Q.578

Q2.Except under approved special instructions, when the line has not been so blocked and a Lorry whether loaded or empty is placed on the line, the Lorry shall be protected when visibility is less than (as per G&SR)

  1. 1200 metres
  2. 1000 metres
  3. 800 metres
  4. 600 metres
Show answer

Answer: (A) 1200 metres

Source: JE (P.Way) Question Bank 2025, Q.627

Q3.Where the visibility is not clear for 1200 metres, in such locations the rail dolly should be worked _________.

  1. Under caution order
  2. Under block protection
  3. without block protection
  4. Under JE/SSE/P.Way supervision
Show answer

Answer: (B) Under block protection

Source: JE (P.Way) Question Bank 2025, Q.644

Q4.The signal for trolley/motor trolley working at night on single line _____ signal shall exhibit

  1. red on one side green on other side
  2. both sides red
  3. red on one side white on other side
  4. Both sides white
Show answer

Answer: (B) both sides red

Source: JE (P.Way) Question Bank 2025, Q.602

Q5.Protection of trollies working without block protection should be done with flagman when the visibility is less than as per IRPWM is

  1. 1200 metres
  2. 1000 metres
  3. 800 metres
  4. 600 metres
Show answer

Answer: (A) 1200 metres

Source: JE (P.Way) Question Bank 2025, Q.611

Q6.Speed potential of Rail Cum Road vehicle (RRV) ________ on track in reverse direction

  1. 10 kmph
  2. 40 kmph
  3. 60 kmph
  4. 80 kmph
Show answer

Answer: (A) 10 kmph

Source: JE (P.Way) Question Bank 2025, Q.652

Q7.In cuttings curved track, the maximum distance apart of trolley refugees shall not exceed ______

  1. 50 metres
  2. 100 metres
  3. 150 metres
  4. 200 metres
Show answer

Answer: (B) 100 metres

Source: JE (P.Way) Question Bank 2025, Q.586

Q8.When two Trollies or more are running together in the same direction on the same line, care shall be taken to ensure that they are kept at least as per G&SR

  1. One OHE mast or 50 metres apart
  2. One OHE mast or 75 metres apart
  3. Two OHE mast or 100 metres apart
  4. Two OHE mast or 150 metres apart
Show answer

Answer: (B) One OHE mast or 75 metres apart

Source: JE (P.Way) Question Bank 2025, Q.619

Q9.The maximum number of men that may be carried on a Motor Trolley shall not exceed _______ is structurally safe

  1. 8
  2. 10
  3. 12
  4. 15
Show answer

Answer: (B) 10

Source: JE (P.Way) Question Bank 2025, Q.594

Q10.In engineering department ______ officials are permitted to use trollies/lorries

  1. All Officers
  2. JE/SSE/P.Way
  3. Gang Mate/Trolleymen
  4. Both
Show answer

Answer: (D) Both

Source: JE (P.Way) Question Bank 2025, Q.561

Q11.Who is the competent authority, to Issue Motor trolley competency certificate to Motor trolley driver is

  1. ADEN
  2. DEN/Sr.DEN
  3. Sr.DEN/Co.ord
  4. Sr.DSO
Show answer

Answer: (D) Sr.DSO

Source: JE (P.Way) Question Bank 2025, Q.569

Q12.When Rail dolley working near LC gate, the person in charge for the working of rail dolly shall be _______

  1. Gang mate
  2. Flag man
  3. Official in charge of rail dolly
  4. Gateman
Show answer

Answer: (C) Official in charge of rail dolly

Source: JE (P.Way) Question Bank 2025, Q.635

‹ Engineering restrictions & indicatorsAll RailPro topicsMaterial trains & working of track machines ›

Preparing for AE / JE exams?
Get new civil engineering vacancies on Telegram, posted automatically every day. Free to join.
Join on Telegram ›