15 questions on estimates, SOR, tenders & contracts, each with the answer and where it comes from. Try each one before you tap Show answer.
Answer them against the clock and see your score with every answer explained.
Start the testQ1.Under GCC Clause 8, the successful tenderer must execute the contract agreement within ______ of notice that it is ready.
Answer: (D) 7 days
Clause 8: the agreement is executed within seven days of notice, and only after a valid Performance Guarantee is submitted.
Source: RailPro e-book Vol 3, page 289
Q2.When negotiations are held on a works tender, they are held with ______
Answer: (D) The L1 tenderer only
Negotiations are held only with L1, the valid, eligible, technically acceptable tenderer with the lowest value.
Source: RailPro e-book Vol 3, page 269
Q3.In a six-digit IRUSSOR item number, what do the first two digits (from the left) indicate?
Answer: (D) Chapter number
The first two digits give the chapter (01–21), then one digit sub-group, two digits main item and the last digit the sub-item.
Source: RailPro e-book Vol 3, page 204
Q4.From 26.11.2019, which schedule of rates applies to railway building, road and horticulture works?
Answer: (C) CPWD Delhi Schedule of Rates (DSR)
The Railway Board adopted the CPWD DSR for building, road and horticulture works; IRUSSOR-2019 covers formation, bridge and P.Way works.
Source: RailPro e-book Vol 3, page 196
Q5.Who is the authority to ban the execution of a particular IRUSSOR item on a Zonal Railway?
Answer: (A) PCE
The PCE may ban unsuitable items by letter, with a copy to EDCE(G), Railway Board.
Source: RailPro e-book Vol 3, page 207
Q6.As per Engineering Code para 1219, works and supplies on contract should preferably be executed according to ______
Answer: (C) Standard specifications and drawings
Para 1219: execution should follow standard specifications and drawings wherever possible, rather than samples.
Source: RailPro e-book Vol 3, page 215
Q7.If L1 withdraws before the work order is placed, what should be done?
Answer: (B) Re-tender
As per CVC instructions, if L1 withdraws before the work order or execution, the work should be re-tendered.
Source: RailPro e-book Vol 3, page 273
Q8.In the Analysis of Rates under IRUSSOR-2019, contractor's profit and overheads are taken at ______
Answer: (B) 15%
AOR components include contractor's profit and overheads at 15% (water charges 1%, cess 1%).
Source: RailPro e-book Vol 3, page 212
Q9.The comparative statement of tenders (para 1252) is prepared by ______
Answer: (C) The Executive Branch and verified by Accounts
Para 1252: the Executive Branch prepares it, Accounts verifies it, and all tenders are tabulated without screening.
Source: RailPro e-book Vol 3, page 243
Q10.Zonal Railways must update the 'Basic Rates' sheet of IRUSSOR-2019 at least once in ______
Answer: (A) two years
Basic rates are updated with Associate Finance concurrence at least once in two years, so each zone has an updated USSOR every two years.
Source: RailPro e-book Vol 3, page 199
Q11.Under IRUSSOR-2019, design mix concrete from M-15 to M-40 is paid ______
Answer: (C) At the same rate irrespective of grade
All design mix grades M-15 to M-40 are paid at the same rate; the grade is for guidance and the site grade is stated in the BOQ.
Source: RailPro e-book Vol 3, page 202
Q12.If there are multiple L1 tenderers, the tender may be awarded to the one with ______
Answer: (A) Higher bid capacity
Higher bid capacity decides; if that is also equal, the one that did more similar work in the last three financial years and the current year is chosen.
Source: RailPro e-book Vol 3, page 274
Q13.Under GCC Clause 22(5), within how many days can a contractor appeal to the Chief Engineer against the Engineer's decision on the meaning of specifications or drawings?
Answer: (D) 7 days
The appeal lies to the CE within 7 days of the decision being intimated; the CE's decision is final (an excepted matter).
Source: RailPro e-book Vol 3, page 225
Q14.If a tenderer is found to have submitted wrong credential information, the agency is barred from business on the entire Indian Railways for ______
Answer: (A) 5 years
The contract is terminated, EMD/PG/SD are forfeited and the agency is barred for 5 years.
Source: RailPro e-book Vol 3, page 278
Q15.How many chapters does IRUSSOR-2019 contain for formation, bridge and P.Way works?
Answer: (D) 21
IRUSSOR-2019 consists of 21 chapters covering formation, bridge and P.Way works.
Source: RailPro e-book Vol 3, page 198