47 questions on works programme, plans & drawings, each with the answer and where it comes from. Try each one before you tap Show answer.
Answer them against the clock and see your score with every answer explained.
Start set 1 Start set 2Q1.On tracings, work that is to be dismantled is shown in ______.
Answer: (C) Thin dotted lines
Existing work to remain is in full line, work to be dismantled in thin dotted lines, and new work in full red lines.
Source: RailPro e-book Vol 3, page 96
Q2.The architectural drawing of a building must invariably indicate ______.
Answer: (B) The number of floors the foundation is designed for
The architectural drawing should invariably show the number of floors for which the foundation is designed; the bar bending schedule belongs to the structural drawing.
Source: RailPro e-book Vol 3, page 92
Q3.In an Engineering Scale Plan (ESP), how is the track shown?
Answer: (C) In single lines only
An ESP is a single-line, latest updated drawing of the station yard; track is shown in single lines only.
Source: RailPro e-book Vol 3, page 123
Q4.Explanations in a completion report are required for savings in a sub-work exceeding ______
Answer: (A) 20% or Rs 1 lakh, whichever is less
Savings above 20% or Rs 1.00 lakh (whichever is less) in any sub-work must be explained.
Source: RailPro e-book Vol 3, page 174
Q5.Replacement of worn-out assets is generally financed from which fund?
Answer: (D) Depreciation Reserve Fund (DRF)
Among the Demand 16 allocations, DRF is meant for replacement of assets.
Source: RailPro e-book Vol 3, page 11
Q6.An Engineering Scale Plan (ESP) must be updated afresh at least once in ______.
Answer: (A) 8 years
All ESPs are updated at least once in 8 years with a fresh drawing number and a note superseding the previous ESP.
Source: RailPro e-book Vol 3, page 127
Q7.In a completion report, explanation is required for an excess under a sub-head exceeding ______
Answer: (D) 10% or Rs 25,000, whichever is less
Remarks are needed for excess above 10% or Rs 25,000 (whichever is less) over the provision under each sub-head.
Source: RailPro e-book Vol 3, page 174
Q8.For a new line, the 'date of opening' is the date on which ______
Answer: (B) Passenger traffic opens on the whole line covered by the estimate
Para 1702: for a new line it is the date of opening of passenger traffic on the whole line included in the construction estimate.
Source: RailPro e-book Vol 3, page 170
Q9.For works other than buildings costing less than Rs 20 lakh, sanctioned completion reports and completion estimates are preserved for ______
Answer: (C) Five years
Para 1720: these are preserved for five years; other reports need not be kept once details are docketed in the Assets/Building Register.
Source: RailPro e-book Vol 3, page 185
Q10.The verified project completion report must be submitted to the Railway Board within ______ after the end of the half-year in which the completion estimate is submitted.
Answer: (C) 18 months
Para 1705: the completion report, verified by the Accounts Officer, goes to the Board within 18 months.
Source: RailPro e-book Vol 3, page 172
Q11.On a drawing, work to be relaid or rebuilt elsewhere on the same plan is shown in ______.
Answer: (B) Full yellow lines
IRWM Para 907 prescribes full yellow lines for work to be relaid or rebuilt elsewhere on the same plan.
Source: RailPro e-book Vol 3, page 96
Q12.Within what time must a completion estimate reach the sanctioning authority after the close of the half-year up to which it shows actual expenditure?
Answer: (A) 4 months
Para 1701: the completion estimate should reach the competent authority within 4 months after the close of that financial half-year.
Source: RailPro e-book Vol 3, page 169
Q13.After completion of a yard work and CRS sanction, how is the completion drawing of the ESP prepared?
Answer: (C) By converting red lines on the original ESP into black lines
The executing agency converts the red lines on the original ESP into black, incorporates changes and gives it a new number after CE/Planning approval.
Source: RailPro e-book Vol 3, page 163
Q14.As per Para 604 of the Engineering Code, detailed traffic and engineering surveys are required for line capacity works costing more than ______ each.
Answer: (A) Rs 5 crore
Detailed traffic and engineering surveys are needed for NL, GC, doubling and other line capacity works costing over Rs 5 crore each.
Source: RailPro e-book Vol 3, page 25
Q15.GM may empower DRM/Dy.CE to approve completion reports in the works register when variations are within ______ of the sanctioned estimate.
Answer: (B) 5%
Note under Form E-1706: DRM/DyCE may be empowered if variations are within 5% of the sanctioned estimate.
Source: RailPro e-book Vol 3, page 174
Q16.If a tracing has to be sent from one office to another, it should be ______
Answer: (A) Rolled and placed in a cardboard cylinder
Para 912(b) IRWM: tracings should not be folded; they are rolled and inserted in a cardboard cylinder.
Source: RailPro e-book Vol 3, page 158
Q17.After completion of work and CRS sanction, how is the completion drawing prepared on the original ESP?
Answer: (C) By converting red lines into black lines
The executing agency submits the completion drawing on the original ESP by converting red lines into black, incorporating changes made during execution.
Source: RailPro e-book Vol 3, page 120
Q18.In the 14-digit IRPSM Project-ID, what does the 9th digit indicate?
Answer: (D) Sanctioning authority
Digits 1-2 give railway, 3-4 division, 5-6 plan head, 7-8 sanction year, 9 sanctioning authority, 10-11 executing agency and 12-14 serial number.
Source: RailPro e-book Vol 3, page 55
Q19.A yard plan not intended to be kept as a roll should not exceed what length?
Answer: (D) 1189 mm
Yard plans are made in widths of 841, 420 or 210 mm, and their length should not exceed 1189 mm unless kept as a roll.
Source: RailPro e-book Vol 3, page 84
Q20.When a work is completed and its accounts closed, what entry is made in the Register of Works?
Answer: (D) A double red ink line below the last entry
Para 1716: a double red ink line is ruled below the last entry with a note 'Work completed, completion report submitted on ...'.
Source: RailPro e-book Vol 3, page 183
Q21.For works costing up to Rs 2.5 crore, how is provision made in the budget documents?
Answer: (D) Lump sum under each Plan Head (LAW Book)
Only a lump sum provision is made per Plan Head without detailing individual works; the detailed list is in the LAW (List of Approved Works) Book.
Source: RailPro e-book Vol 3, page 29
Q22.For a bridge on an important river without a correct survey, the river should be surveyed for what distances?
Answer: (D) 8 km upstream and 2 km downstream
The river is surveyed 8 km upstream and 2 km downstream, measured at right angles to the railway centre line.
Source: RailPro e-book Vol 3, page 93
Q23.Road safety works for Road Over/Under Bridges are booked under which Plan Head?
Answer: (C) PH 30
PH 29 is Road Safety Works - Level Crossings and PH 30 is Road Safety Works - ROB/RUB.
Source: RailPro e-book Vol 3, page 18
Q24.The application to CRS for an ROB/RUB executed by the open line Railway should be submitted by ______.
Answer: (C) CBE
Per CRS Central Circle letter (2018), applications for ROB/RUB/RFO/bridges executed by Railway are submitted by CBE; FOBs by division are submitted by DRM.
Source: RailPro e-book Vol 3, page 135
Q25.For a railway project costing more than Rs 1 crore, the completion estimate is prepared at the end of one of the first ______ financial half-years after the date of opening.
Answer: (D) three
Para 1701: the estimate is closed and the completion estimate prepared at the end of one of the first three financial half-years after opening.
Source: RailPro e-book Vol 3, page 167
Q26.Departure from a standard drawing is permitted only with the specific permission of ______.
Answer: (C) Chief Engineer
As per IRWM Para 901, standard drawings shall not be departed from without the specific permission of the Chief Engineer.
Source: RailPro e-book Vol 3, page 80
Q27.Under which demand of the Railway budget are works for acquisition, construction and replacement of assets (Works Programme) provided?
Answer: (A) Demand No. 16
The Capital Budget (Demand No. 16) covers assets acquisition, construction and replacement, including the Works Programme.
Source: RailPro e-book Vol 3, page 10
Q28.Plan Head 31 of the Works Programme relates to ______.
Answer: (D) Track renewals
PH 31 is Track Renewals; PH 30 is ROB/RUB, PH 32 Bridge Works and PH 33 S&T works.
Source: RailPro e-book Vol 3, page 18
Q29.Besides levels and soil details, what note must always be added to the completion drawing of a bridge?
Answer: (D) Source from which the datum level was obtained
Para 911(d) IRWM: in all cases a note must state from where the datum level has been obtained.
Source: RailPro e-book Vol 3, page 157
Q30.Under Demand 16, works of category I3 are sanctioned by ______.
Answer: (C) GM
I1 is Pink Book work sanctioned by RB, I2 sanctioned by RB but printed in LAW book, I3 sanctioned by GM and I4 by DRM.
Source: RailPro e-book Vol 3, page 27
Q31.On completion-drawing prints, alterations made from the working plans during execution are to be marked in ______
Answer: (A) Red ink
Para 911 of IRWM requires alterations or modifications from the working plans to be marked on the prints in red ink.
Source: RailPro e-book Vol 3, page 155
Q32.In an ESP, from which point are the distances of turnouts, bridges, LCs and km posts measured?
Answer: (B) Centre line of the station
The centre line of the station is taken as zero chainage and all distances are marked from it.
Source: RailPro e-book Vol 3, page 124
Q33.In Railway Board, new works costing less than Rs 20 crore are approved by ______.
Answer: (B) Additional Members' (AMs') Committee
Works below Rs 20 crore are approved by the AMs' Committee; works of Rs 20 crore and above are processed on file for Board and MR's approval.
Source: RailPro e-book Vol 3, page 33
Q34.What is the significance of a work's unique ID generated through IRPSM?
Answer: (A) Without it the work has no valid sanction
Any work without the IRPSM-generated unique ID has no sanctity of sanction; the ID must be quoted in plans, estimates, tenders, contracts, MBs and bills.
Source: RailPro e-book Vol 3, page 54
Q35.If final land-acquisition charges are likely to be delayed, the completion report of a project may be ______
Answer: (A) Submitted in two parts: one excluding land and one for land
Para 1719: it may be submitted in two parts, but both are treated as one report for allocation and sanction.
Source: RailPro e-book Vol 3, page 184
Q36.Under the umbrella work system, a Detailed Project Report (DPR) is compulsory for itemised works costing more than ______.
Answer: (B) Rs 50 crore
For itemised works under umbrella sanctions, a DPR is compulsory for works above Rs 50 crore.
Source: RailPro e-book Vol 3, page 59
Q37.What is the size of the title block on a railway engineering drawing?
Answer: (B) 170 mm x 65 mm
The title block, placed at the bottom right-hand corner, is 170 mm x 65 mm.
Source: RailPro e-book Vol 3, page 84
Q38.After a modification is approved on the original ESP, how is the drawing number treated?
Answer: (D) Same number with suffix ALT-1, ALT-2 etc.
For modifications incorporated on the original ESP, the drawing number remains the same with suffix ALT-1, ALT-2 etc.
Source: RailPro e-book Vol 3, page 131
Q39.Additions and alterations to an existing plan should be shown in which colour?
Answer: (C) Red
Additions and alterations are shown in red and approved by the authority who approved the original plan.
Source: RailPro e-book Vol 3, page 82
Q40.As a rule, the accounts of a completed work should be closed how long after the date of completion?
Answer: (C) Six months
Para 1708: outstanding debits/credits are adjusted within three months, and the accounts are closed six months after completion.
Source: RailPro e-book Vol 3, page 176
Q41.Index plan and section are drawn to what scale?
Answer: (A) 0.5 km to 1 cm horizontal, 10 m to 1 cm vertical
Index plan and section use 0.5 km to a cm horizontally and 10 m to a cm vertically, on the same sheet.
Source: RailPro e-book Vol 3, page 108
Q42.Which drawing sheet size is prescribed for plans included in Works Programme booklets for handy reference?
Answer: (A) A4 (210 x 297 mm)
Table 9.1 prescribes A4 for plans in Works Programme booklets and PERT charts of works of limited activities.
Source: RailPro e-book Vol 3, page 85
Q43.Proposals for which of the following works are initiated at Railway Board level and not proposed by zonal railways?
Answer: (A) Gauge conversion
New lines, gauge conversion, doubling and railway electrification proposals are initiated at Railway Board level.
Source: RailPro e-book Vol 3, page 24
Q44.Who coordinates the Works Programme at the divisional level?
Answer: (B) Sr. DEN/Co
Works Programme coordinators are EDCE(G) at Railway Board, CE/Planning at zonal level and Sr. DEN/Co at division.
Source: RailPro e-book Vol 3, page 22
Q45.A drawing prepared in the division and submitted for CE office approval carries an 'R' number. What number is allotted after CE office approval?
Answer: (D) P (pucca) number
Divisional drawings bear an R number; after approval by CE office a P (pucca/GM(W)) number is allotted and the original tracing kept there.
Source: RailPro e-book Vol 3, page 103
Q46.Plans of station yards requiring special design are drawn to what scale?
Answer: (A) 10 m to 1 cm
For stations requiring special design, a station yard plan to 10 m to a cm is required showing all lines, sidings, platforms, buildings, signals etc.
Source: RailPro e-book Vol 3, page 110
Q47.In the ESP colour scheme, future Phase III works are shown in ______.
Answer: (B) Blue
Existing details are in black, proposed work in red, works to be dismantled in black dotted lines, Phase II in green and Phase III in blue.
Source: RailPro e-book Vol 3, page 125