Works programme, plans & drawings — questions with answers

47 questions on works programme, plans & drawings, each with the answer and where it comes from. Try each one before you tap Show answer.

Take these as a scored test

Answer them against the clock and see your score with every answer explained.

Start set 1 Start set 2

Questions

Q1.On tracings, work that is to be dismantled is shown in ______.

  1. Full red lines
  2. Broken red lines
  3. Thin dotted lines
  4. Full yellow lines
Show answer

Answer: (C) Thin dotted lines

Existing work to remain is in full line, work to be dismantled in thin dotted lines, and new work in full red lines.

Source: RailPro e-book Vol 3, page 96

Q2.The architectural drawing of a building must invariably indicate ______.

  1. The bar bending schedule
  2. The number of floors the foundation is designed for
  3. The bore log details
  4. The tender value of the work
Show answer

Answer: (B) The number of floors the foundation is designed for

The architectural drawing should invariably show the number of floors for which the foundation is designed; the bar bending schedule belongs to the structural drawing.

Source: RailPro e-book Vol 3, page 92

Q3.In an Engineering Scale Plan (ESP), how is the track shown?

  1. In double lines to scale
  2. As rail centre lines with sleepers
  3. In single lines only
  4. In colour-coded double lines
Show answer

Answer: (C) In single lines only

An ESP is a single-line, latest updated drawing of the station yard; track is shown in single lines only.

Source: RailPro e-book Vol 3, page 123

Q4.Explanations in a completion report are required for savings in a sub-work exceeding ______

  1. 20% or Rs 1 lakh, whichever is less
  2. 10% or Rs 25,000, whichever is less
  3. 5% or Rs 50,000, whichever is more
  4. 25% or Rs 2 lakh, whichever is less
Show answer

Answer: (A) 20% or Rs 1 lakh, whichever is less

Savings above 20% or Rs 1.00 lakh (whichever is less) in any sub-work must be explained.

Source: RailPro e-book Vol 3, page 174

Q5.Replacement of worn-out assets is generally financed from which fund?

  1. Development Fund (DF)
  2. Capital Fund (CF)
  3. Open Line Works Revenue (OLWR)
  4. Depreciation Reserve Fund (DRF)
Show answer

Answer: (D) Depreciation Reserve Fund (DRF)

Among the Demand 16 allocations, DRF is meant for replacement of assets.

Source: RailPro e-book Vol 3, page 11

Q6.An Engineering Scale Plan (ESP) must be updated afresh at least once in ______.

  1. 8 years
  2. 3 years
  3. 5 years
  4. 10 years
Show answer

Answer: (A) 8 years

All ESPs are updated at least once in 8 years with a fresh drawing number and a note superseding the previous ESP.

Source: RailPro e-book Vol 3, page 127

Q7.In a completion report, explanation is required for an excess under a sub-head exceeding ______

  1. 5% or Rs 10,000, whichever is more
  2. 10% or Rs 1 lakh, whichever is more
  3. 20% or Rs 25,000, whichever is less
  4. 10% or Rs 25,000, whichever is less
Show answer

Answer: (D) 10% or Rs 25,000, whichever is less

Remarks are needed for excess above 10% or Rs 25,000 (whichever is less) over the provision under each sub-head.

Source: RailPro e-book Vol 3, page 174

Q8.For a new line, the 'date of opening' is the date on which ______

  1. CRS inspection is completed
  2. Passenger traffic opens on the whole line covered by the estimate
  3. The first material train runs
  4. The last contract is closed
Show answer

Answer: (B) Passenger traffic opens on the whole line covered by the estimate

Para 1702: for a new line it is the date of opening of passenger traffic on the whole line included in the construction estimate.

Source: RailPro e-book Vol 3, page 170

Q9.For works other than buildings costing less than Rs 20 lakh, sanctioned completion reports and completion estimates are preserved for ______

  1. Three years
  2. Ten years
  3. Five years
  4. Permanently
Show answer

Answer: (C) Five years

Para 1720: these are preserved for five years; other reports need not be kept once details are docketed in the Assets/Building Register.

Source: RailPro e-book Vol 3, page 185

Q10.The verified project completion report must be submitted to the Railway Board within ______ after the end of the half-year in which the completion estimate is submitted.

  1. 6 months
  2. 12 months
  3. 18 months
  4. 24 months
Show answer

Answer: (C) 18 months

Para 1705: the completion report, verified by the Accounts Officer, goes to the Board within 18 months.

Source: RailPro e-book Vol 3, page 172

Q11.On a drawing, work to be relaid or rebuilt elsewhere on the same plan is shown in ______.

  1. Full red lines
  2. Full yellow lines
  3. Broken red lines
  4. Thin dotted lines
Show answer

Answer: (B) Full yellow lines

IRWM Para 907 prescribes full yellow lines for work to be relaid or rebuilt elsewhere on the same plan.

Source: RailPro e-book Vol 3, page 96

Q12.Within what time must a completion estimate reach the sanctioning authority after the close of the half-year up to which it shows actual expenditure?

  1. 4 months
  2. 2 months
  3. 6 months
  4. 12 months
Show answer

Answer: (A) 4 months

Para 1701: the completion estimate should reach the competent authority within 4 months after the close of that financial half-year.

Source: RailPro e-book Vol 3, page 169

Q13.After completion of a yard work and CRS sanction, how is the completion drawing of the ESP prepared?

  1. A fresh tracing in blue lines
  2. By erasing all red lines
  3. By converting red lines on the original ESP into black lines
  4. By overprinting in green
Show answer

Answer: (C) By converting red lines on the original ESP into black lines

The executing agency converts the red lines on the original ESP into black, incorporates changes and gives it a new number after CE/Planning approval.

Source: RailPro e-book Vol 3, page 163

Q14.As per Para 604 of the Engineering Code, detailed traffic and engineering surveys are required for line capacity works costing more than ______ each.

  1. Rs 5 crore
  2. Rs 1 crore
  3. Rs 2.5 crore
  4. Rs 20 crore
Show answer

Answer: (A) Rs 5 crore

Detailed traffic and engineering surveys are needed for NL, GC, doubling and other line capacity works costing over Rs 5 crore each.

Source: RailPro e-book Vol 3, page 25

Q15.GM may empower DRM/Dy.CE to approve completion reports in the works register when variations are within ______ of the sanctioned estimate.

  1. 2%
  2. 5%
  3. 10%
  4. 15%
Show answer

Answer: (B) 5%

Note under Form E-1706: DRM/DyCE may be empowered if variations are within 5% of the sanctioned estimate.

Source: RailPro e-book Vol 3, page 174

Q16.If a tracing has to be sent from one office to another, it should be ______

  1. Rolled and placed in a cardboard cylinder
  2. Folded as per Annexure 9.2
  3. Folded in four and sent in an envelope
  4. Cut into sheets and sent separately
Show answer

Answer: (A) Rolled and placed in a cardboard cylinder

Para 912(b) IRWM: tracings should not be folded; they are rolled and inserted in a cardboard cylinder.

Source: RailPro e-book Vol 3, page 158

Q17.After completion of work and CRS sanction, how is the completion drawing prepared on the original ESP?

  1. By redrawing in green lines
  2. By adding yellow lines for new work
  3. By converting red lines into black lines
  4. By deleting the proposed work
Show answer

Answer: (C) By converting red lines into black lines

The executing agency submits the completion drawing on the original ESP by converting red lines into black, incorporating changes made during execution.

Source: RailPro e-book Vol 3, page 120

Q18.In the 14-digit IRPSM Project-ID, what does the 9th digit indicate?

  1. Plan Head
  2. Executing agency
  3. Sanction year
  4. Sanctioning authority
Show answer

Answer: (D) Sanctioning authority

Digits 1-2 give railway, 3-4 division, 5-6 plan head, 7-8 sanction year, 9 sanctioning authority, 10-11 executing agency and 12-14 serial number.

Source: RailPro e-book Vol 3, page 55

Q19.A yard plan not intended to be kept as a roll should not exceed what length?

  1. 841 mm
  2. 1000 mm
  3. 1500 mm
  4. 1189 mm
Show answer

Answer: (D) 1189 mm

Yard plans are made in widths of 841, 420 or 210 mm, and their length should not exceed 1189 mm unless kept as a roll.

Source: RailPro e-book Vol 3, page 84

Q20.When a work is completed and its accounts closed, what entry is made in the Register of Works?

  1. A single blue line and the AEN's signature
  2. A rubber stamp 'Closed'
  3. The page is cancelled diagonally
  4. A double red ink line below the last entry
Show answer

Answer: (D) A double red ink line below the last entry

Para 1716: a double red ink line is ruled below the last entry with a note 'Work completed, completion report submitted on ...'.

Source: RailPro e-book Vol 3, page 183

Q21.For works costing up to Rs 2.5 crore, how is provision made in the budget documents?

  1. Itemised listing in the Pink Book
  2. Separate demand for each work
  3. No provision; funded from revenue
  4. Lump sum under each Plan Head (LAW Book)
Show answer

Answer: (D) Lump sum under each Plan Head (LAW Book)

Only a lump sum provision is made per Plan Head without detailing individual works; the detailed list is in the LAW (List of Approved Works) Book.

Source: RailPro e-book Vol 3, page 29

Q22.For a bridge on an important river without a correct survey, the river should be surveyed for what distances?

  1. 2 km upstream and 8 km downstream
  2. 5 km upstream and 5 km downstream
  3. 10 km upstream and 1 km downstream
  4. 8 km upstream and 2 km downstream
Show answer

Answer: (D) 8 km upstream and 2 km downstream

The river is surveyed 8 km upstream and 2 km downstream, measured at right angles to the railway centre line.

Source: RailPro e-book Vol 3, page 93

Q23.Road safety works for Road Over/Under Bridges are booked under which Plan Head?

  1. PH 29
  2. PH 32
  3. PH 30
  4. PH 64
Show answer

Answer: (C) PH 30

PH 29 is Road Safety Works - Level Crossings and PH 30 is Road Safety Works - ROB/RUB.

Source: RailPro e-book Vol 3, page 18

Q24.The application to CRS for an ROB/RUB executed by the open line Railway should be submitted by ______.

  1. DRM
  2. CE/Construction
  3. CBE
  4. PCE
Show answer

Answer: (C) CBE

Per CRS Central Circle letter (2018), applications for ROB/RUB/RFO/bridges executed by Railway are submitted by CBE; FOBs by division are submitted by DRM.

Source: RailPro e-book Vol 3, page 135

Q25.For a railway project costing more than Rs 1 crore, the completion estimate is prepared at the end of one of the first ______ financial half-years after the date of opening.

  1. two
  2. four
  3. six
  4. three
Show answer

Answer: (D) three

Para 1701: the estimate is closed and the completion estimate prepared at the end of one of the first three financial half-years after opening.

Source: RailPro e-book Vol 3, page 167

Q26.Departure from a standard drawing is permitted only with the specific permission of ______.

  1. Divisional Engineer
  2. ADEN
  3. Chief Engineer
  4. RDSO
Show answer

Answer: (C) Chief Engineer

As per IRWM Para 901, standard drawings shall not be departed from without the specific permission of the Chief Engineer.

Source: RailPro e-book Vol 3, page 80

Q27.Under which demand of the Railway budget are works for acquisition, construction and replacement of assets (Works Programme) provided?

  1. Demand No. 16
  2. Demand No. 3
  3. Demand No. 11
  4. Demand No. 13
Show answer

Answer: (A) Demand No. 16

The Capital Budget (Demand No. 16) covers assets acquisition, construction and replacement, including the Works Programme.

Source: RailPro e-book Vol 3, page 10

Q28.Plan Head 31 of the Works Programme relates to ______.

  1. Bridge works
  2. Road over/under bridges
  3. Signalling & telecom works
  4. Track renewals
Show answer

Answer: (D) Track renewals

PH 31 is Track Renewals; PH 30 is ROB/RUB, PH 32 Bridge Works and PH 33 S&T works.

Source: RailPro e-book Vol 3, page 18

Q29.Besides levels and soil details, what note must always be added to the completion drawing of a bridge?

  1. Name of the contractor
  2. Date of the first train
  3. Rate of the agreement
  4. Source from which the datum level was obtained
Show answer

Answer: (D) Source from which the datum level was obtained

Para 911(d) IRWM: in all cases a note must state from where the datum level has been obtained.

Source: RailPro e-book Vol 3, page 157

Q30.Under Demand 16, works of category I3 are sanctioned by ______.

  1. Railway Board
  2. DRM
  3. GM
  4. PCE
Show answer

Answer: (C) GM

I1 is Pink Book work sanctioned by RB, I2 sanctioned by RB but printed in LAW book, I3 sanctioned by GM and I4 by DRM.

Source: RailPro e-book Vol 3, page 27

Q31.On completion-drawing prints, alterations made from the working plans during execution are to be marked in ______

  1. Red ink
  2. Blue ink
  3. Green ink
  4. Black ink
Show answer

Answer: (A) Red ink

Para 911 of IRWM requires alterations or modifications from the working plans to be marked on the prints in red ink.

Source: RailPro e-book Vol 3, page 155

Q32.In an ESP, from which point are the distances of turnouts, bridges, LCs and km posts measured?

  1. Home signal
  2. Centre line of the station
  3. First facing point
  4. Station building end
Show answer

Answer: (B) Centre line of the station

The centre line of the station is taken as zero chainage and all distances are marked from it.

Source: RailPro e-book Vol 3, page 124

Q33.In Railway Board, new works costing less than Rs 20 crore are approved by ______.

  1. Minister of Railways directly
  2. Additional Members' (AMs') Committee
  3. Ministry of Finance
  4. Zonal GM
Show answer

Answer: (B) Additional Members' (AMs') Committee

Works below Rs 20 crore are approved by the AMs' Committee; works of Rs 20 crore and above are processed on file for Board and MR's approval.

Source: RailPro e-book Vol 3, page 33

Q34.What is the significance of a work's unique ID generated through IRPSM?

  1. Without it the work has no valid sanction
  2. It is used only for stores indents
  3. It is optional for works below Rs 1 crore
  4. It is assigned only after completion
Show answer

Answer: (A) Without it the work has no valid sanction

Any work without the IRPSM-generated unique ID has no sanctity of sanction; the ID must be quoted in plans, estimates, tenders, contracts, MBs and bills.

Source: RailPro e-book Vol 3, page 54

Q35.If final land-acquisition charges are likely to be delayed, the completion report of a project may be ______

  1. Submitted in two parts: one excluding land and one for land
  2. Withheld until land charges are settled
  3. Submitted without any land figures at all
  4. Sanctioned by the Accounts Officer alone
Show answer

Answer: (A) Submitted in two parts: one excluding land and one for land

Para 1719: it may be submitted in two parts, but both are treated as one report for allocation and sanction.

Source: RailPro e-book Vol 3, page 184

Q36.Under the umbrella work system, a Detailed Project Report (DPR) is compulsory for itemised works costing more than ______.

  1. Rs 2.5 crore
  2. Rs 50 crore
  3. Rs 10 crore
  4. Rs 20 crore
Show answer

Answer: (B) Rs 50 crore

For itemised works under umbrella sanctions, a DPR is compulsory for works above Rs 50 crore.

Source: RailPro e-book Vol 3, page 59

Q37.What is the size of the title block on a railway engineering drawing?

  1. 150 mm x 50 mm
  2. 170 mm x 65 mm
  3. 185 mm x 75 mm
  4. 210 mm x 100 mm
Show answer

Answer: (B) 170 mm x 65 mm

The title block, placed at the bottom right-hand corner, is 170 mm x 65 mm.

Source: RailPro e-book Vol 3, page 84

Q38.After a modification is approved on the original ESP, how is the drawing number treated?

  1. A fresh pucca number is allotted
  2. R number is re-allotted
  3. Number is cancelled and redrawn
  4. Same number with suffix ALT-1, ALT-2 etc.
Show answer

Answer: (D) Same number with suffix ALT-1, ALT-2 etc.

For modifications incorporated on the original ESP, the drawing number remains the same with suffix ALT-1, ALT-2 etc.

Source: RailPro e-book Vol 3, page 131

Q39.Additions and alterations to an existing plan should be shown in which colour?

  1. Green
  2. Blue
  3. Red
  4. Yellow
Show answer

Answer: (C) Red

Additions and alterations are shown in red and approved by the authority who approved the original plan.

Source: RailPro e-book Vol 3, page 82

Q40.As a rule, the accounts of a completed work should be closed how long after the date of completion?

  1. One month
  2. Three months
  3. Six months
  4. One year
Show answer

Answer: (C) Six months

Para 1708: outstanding debits/credits are adjusted within three months, and the accounts are closed six months after completion.

Source: RailPro e-book Vol 3, page 176

Q41.Index plan and section are drawn to what scale?

  1. 0.5 km to 1 cm horizontal, 10 m to 1 cm vertical
  2. 50 m to 1 cm horizontal, 5 m to 1 cm vertical
  3. 1 km to 1 cm horizontal, 20 m to 1 cm vertical
  4. 10 m to 1 cm horizontal and vertical
Show answer

Answer: (A) 0.5 km to 1 cm horizontal, 10 m to 1 cm vertical

Index plan and section use 0.5 km to a cm horizontally and 10 m to a cm vertically, on the same sheet.

Source: RailPro e-book Vol 3, page 108

Q42.Which drawing sheet size is prescribed for plans included in Works Programme booklets for handy reference?

  1. A4 (210 x 297 mm)
  2. A3 (297 x 420 mm)
  3. A2 (420 x 594 mm)
  4. A1 (594 x 841 mm)
Show answer

Answer: (A) A4 (210 x 297 mm)

Table 9.1 prescribes A4 for plans in Works Programme booklets and PERT charts of works of limited activities.

Source: RailPro e-book Vol 3, page 85

Q43.Proposals for which of the following works are initiated at Railway Board level and not proposed by zonal railways?

  1. Gauge conversion
  2. Track renewals
  3. Passenger amenities
  4. Staff quarters
Show answer

Answer: (A) Gauge conversion

New lines, gauge conversion, doubling and railway electrification proposals are initiated at Railway Board level.

Source: RailPro e-book Vol 3, page 24

Q44.Who coordinates the Works Programme at the divisional level?

  1. Sr. DOM
  2. Sr. DEN/Co
  3. Sr. DFM
  4. ADRM
Show answer

Answer: (B) Sr. DEN/Co

Works Programme coordinators are EDCE(G) at Railway Board, CE/Planning at zonal level and Sr. DEN/Co at division.

Source: RailPro e-book Vol 3, page 22

Q45.A drawing prepared in the division and submitted for CE office approval carries an 'R' number. What number is allotted after CE office approval?

  1. C (completion) number
  2. A (alteration) number
  3. S (standard) number
  4. P (pucca) number
Show answer

Answer: (D) P (pucca) number

Divisional drawings bear an R number; after approval by CE office a P (pucca/GM(W)) number is allotted and the original tracing kept there.

Source: RailPro e-book Vol 3, page 103

Q46.Plans of station yards requiring special design are drawn to what scale?

  1. 10 m to 1 cm
  2. 5 m to 1 cm
  3. 25 m to 1 cm
  4. 50 m to 1 cm
Show answer

Answer: (A) 10 m to 1 cm

For stations requiring special design, a station yard plan to 10 m to a cm is required showing all lines, sidings, platforms, buildings, signals etc.

Source: RailPro e-book Vol 3, page 110

Q47.In the ESP colour scheme, future Phase III works are shown in ______.

  1. Green
  2. Blue
  3. Red
  4. Yellow
Show answer

Answer: (B) Blue

Existing details are in black, proposed work in red, works to be dismantled in black dotted lines, Phase II in green and Phase III in blue.

Source: RailPro e-book Vol 3, page 125

‹ Accidents, monsoon, disasters & first aidAll RailPro topicsEstimates, SOR, tenders & contracts ›